News and Announcements

Dune Restoration

Post Installation is Now Complete!

Added: 5/16/2017

The installation of all the posts is now complete. The Vibro-Hammer pounded the last posts on Monday and the heavy machinery has now been retired! The work on the decking and stairs will continue with... read more


Clicker Beach

Added: 5/9/2017

Preparing to drill for the posts at Clicker Beach! read more


Progress Continues Southward

Added: 5/7/2017

Post installation is continuing south from the Comfort Station. This is a birds' eye view looking to the south as the drilling for the posts is being done. Heavy equipment continues up and down the... read more


Pole Installation Contiues

Added: 5/2/2017

Poles can be seen down the beach from Grande Mer and now extending south of the Comfort Station. Good progress continues to be made by the construction crews. read more


Good Progress is Being Made!

Added: 5/1/2017

This is a photo of the post installation at the Comfort Station. Two crews are making good progress with the installation down the beach. When the post installation has been completed, the decking... read more


Please Stay Off the Dunes!

Added: 4/28/2017

The sand dunes have now been re-built and re-planted with tender young plants. It is most important that the plantings are not disturbed so they will take hold in the sand. Until the heavy equipment... read more


Installing the Walkover Posts

Added: 4/28/2017

This is the beginning of the post installation at Portofino last evening! read more


Pre-positioning the posts

Added: 4/27/2017

Surveying has been done and the contractor has begun distributing the posts for installation. read more


Walkover Prep

Added: 4/26/2017

Equipment and materials staged at Jungle Hut for post installation. read more


Dune Restoration Project Update

Added: 4/21/2017

Phase 1 of the dune sand project is complete. Phase 1 of the dune planting project is complete. The HDOA has contracted to repair the 29 occupied dune walkovers along the beach. The contractor... read more


Dune Project Update

Added: 4/11/2017

Dune Restoration Update The dune planting contractor started yesterday afternoon and will be installing FDEP approved native plants in the new dune all week. Please be advised, the Hammock Dunes... read more


Dune Profiling Continues

Added: 4/10/2017

Bulldozers are now putting the finishing touches on the dune and beach area... read more


Sand, Sand and more Sand!

Added: 4/3/2017

Piling the sand to ready the dune for profiling in the first photo...the bulldozer at work moving the sand to the predetermined profile in the second photo... read more


Flyover of the Dune Restoration Project

Added: 3/31/2017

At the time of the flyover, approximately 3 weeks into the project, 3000 truckloads of sand had been delivered. Good progress is being made to restore our dunes! read more


That is a big truck!

Added: 3/28/2017

Now that the sand has been compacted this truck as been added to the crew.. read more


1 2 Next
Showing Articles 1 to 15 of 20
  • Hammock Dunes Owners' Association
  • 2 Camino del Mar
  • Palm Coast, Florida 32137
  • Site Map ~ Contact Us

The Hammock DunesTM name, design, logo, and clock tower icon are registered trademarks of the Hammock Dunes Owners' Association (HDOA). Any use without the express written permission of the HDOA is strictly prohibited.
© 2014-2016 HDOA. All Rights Reserved.